NCC to build out Oslo Gardermoen Airport for SEK 475m
NCC Construction Norway has signed an agreement with Oslo Lufthavn AS for foundation engineering and concrete work at Gardermoen Airport for a total of approximately SEK 475 million, which will be registered among orders in the first quarter of 2012. The work is scheduled to continue for three years and is a phase in the expansion of the Gardermoen Airport.
Gardermoen is beginning to reach its capacity ceiling and will be expanded with a new pier, thus expanding arrival and departure halls to increase capacity. NCC’s contract pertains to the expansion of the Sentralbygning Vest (Central Building West).
Work will commence in April 2012 and is scheduled to continue until February 2015.
Gardermoen is beginning to reach its capacity ceiling and will be expanded with a new pier, thus expanding arrival and departure halls to increase capacity. NCC’s contract pertains to the expansion of the Sentralbygning Vest (Central Building West).
Work will commence in April 2012 and is scheduled to continue until February 2015.